Chevron

STAR DEEP WATER PETROLEUM/Design of Work Platform and Rain Roof Cover For the Lact Sample Point on Agbami FPSO

  • Company request for a design of a prefabricated access platform with a roof extension to cover the LACT sample point area on Agbami FPSO.
  • The platforms will be like the prefabricated platforms for the turbine enclosure entrance door platforms. This platform should be caple of supporting the weight of a minimum of two persons.

The rain roof cover for the sample point will cover the sample takeoff point to avoid sample contamination during the rainy season.

Status: Completed

Facilities Information Gap Assessment and Gap Closure(DW PSI PROJECT) AGBAMI

COMPANY wishes to gather, update and create facilities information for its existing and new facilities. This is in support of its plan to implement a Facilities Information Management (FIM) process in compliance with Chevron Upstream and Gas standards (CUG). The objective of this process is to ensure that a centralized information management system is in place for developing and maintaining facilities information within the business unit.

Status: On-going

Seawater Lift System FRP Piping Solution Project

  • To fit 2 Accumulators in to the main sea water lift flow lines located at 1PMD running from the sea water lift pump discharges to the 30” header on 3P level 2.
  • Design the pipe work and the accumulator vessels with all relevant structural equipment required using an on location NO hot work philosophy .
  • To complete detailed engineering design for review and construction review of Piping, Vessel design and structural works.
  • To complete all flow calculations and review with DWFE engineers.

Status: Completed

As-Built/Piping Inspection Drawings for Agbami FPSO (Batch A – G)

Equipment and Piping Inspection Drawings for corrosion groups detailed in the Colored PFD provided by Company: AGB-CC-011(600 Inspection Drawings), AGB-cc-012 (150 Inspection Drawings).

Status: Completed

Design of Work Platform and Rain Roof Cover For the Lact Sample Point on Agbami FPSO

  • Company request for a design of a prefabricated access platform with a roof extension to cover the LACT sample point area on Agbami FPSO.
  • The platforms will be like the prefabricated platforms for the turbine enclosure entrance door platforms. This platform should be caple of supporting the weight of a minimum of two persons.
  • The rain roof cover for the sample point will cover the sample takeoff point to avoid sample contamination during the rainy season.

Status: Completed

STABILIZER THERMODYNAMIC BALANCING PROJECT

Project is designed to put in a 14” bypass connection from LP sepa-rator to the LP suction scrubber on 3 gas trains and install a 3” line between the deoxygenated line to the LP separator on 3 lines.

To complete conceptual / feed design for review and construction review. Of Piping and structural works.  To complete all flow calcu-lations and review with DWFE en-gineers. On approval of concept and first design to complete detail design ready for fabrication. This will require a site visit to get meas-urements and field survey.

Status: On-going

Engineering Design of Macerator Installation

  • MOBILISATION, SITE VISIT/INVESTIGATION.
  • Installation study
  • Tie-in Study (Portable water & Utility Air)
  • Basis of Design
  • Eng. Management and Cost Estimation
  • Progress review meeting with client (6 weeks x 3)
  • Constructibility/Installation review (if necessary)

Status: Completed