Seawater Lift System FRP Piping Solution Project

  • Year

    2016
  • Project Status

    Completed
  • To fit 2 Accumulators in to the main sea water lift flow lines located at 1PMD running from the sea water lift pump discharges to the 30” header on 3P level 2.
  • Design the pipe work and the accumulator vessels with all relevant structural equipment required using an on location NO hot work philosophy .
  • To complete detailed engineering design for review and construction review of Piping, Vessel design and structural works.
  • To complete all flow calculations and review with DWFE engineers.