STABILIZER THERMODYNAMIC BALANCING PROJECT

  • Year

    2016
  • Project Status

    On-going

Project is designed to put in a 14” bypass connection from LP sepa-rator to the LP suction scrubber on 3 gas trains and install a 3” line between the deoxygenated line to the LP separator on 3 lines.

To complete conceptual / feed design for review and construction review. Of Piping and structural works.  To complete all flow calcu-lations and review with DWFE en-gineers. On approval of concept and first design to complete detail design ready for fabrication. This will require a site visit to get meas-urements and field survey.